/
Gantt Configuration
Gantt Configuration
Some key values of a task are calculated as follows:
Start Date
Start dates of a task is calculated as follows:
- If a "RQ Start DateTime" Custom field is specified in Administration, its value will be used.
- If above is not true, and if task 'Status' is 'In Progress', then it considers the date when it was converted from 'To Do' to 'In Progress' as the start date.
- If above not true, then it uses 'Created Date' as start date.
- If none of the above is true, then uses Today's date as start date.
End Date
End Date of a task is calculated as follows:
- If a "RQ End DateTime" Custom field is specified in Administration, its value will be used.
- If above is not true, and if 'Resolution' state is 'Resolved', then it considers Resolved Date as end date.
- If above not true, then it uses last updated, and due date based on these conditions:
- if updated date > due date date, then updated date is set as end date.
- if updated date < due date date, then due date date is set as end date.
Sort Order
Custom Field - Sort Order
Progress
Custom Field - Progress Percent
Takes values 0 to 100.
Indent Level
Custom Field - Parent ID
, multiple selections available,
Related content
Crystal Gantt VS Crystal Gantt Pro
Crystal Gantt VS Crystal Gantt Pro
Read with this
Gantt Initial Task Value Calculation
Gantt Initial Task Value Calculation
More like this
Solution for Next-Gen Project
Solution for Next-Gen Project
More like this
Release Notes
Release Notes
More like this
ProjectGantt
ProjectGantt
More like this
Default hierarchy of items in Gantt
Default hierarchy of items in Gantt
More like this